46
90% range 44.7–47.7
Turner Construction Company
Primary kind of workCommercial new
activelow confidence
Sub-scores
Inspections45
typical
Failed / re-inspection results on 46% of inspections vs 37% expected for similar jobs
Plan quality / Revisions40
worse than peers
3.86 plan send-backs / revision events per permit vs 1.74 expected for similar jobs
Time to permit45
typical
Median 55 days to approval vs 59.5 days peer median (1.59× after adjusting for kind of work)
Completion—
not enough data
More: compliance & reliability
Compliance39
worse than peers
0.43 license/insurance/stop-work type holds per permit vs 0.17 expected
Reliability65
better than peers
3% of inspections cancelled vs 6% expected
Ann Arbor activity & plain stats
Permits in scored set
6
Last 3 years
3
Last 12 months
1
Years active
4
2015–2026
Median days to approval
55.0
peer median 59.5
Permits needing a revision
67%
Permits with a failed / re-inspection
83%
Inspections on record
325
Job mix
Commercial alterations 50% Commercial new 50%
Sample permit records
| Permit | Kind of work | Applied | Status | Days to approval | Notes |
|---|---|---|---|---|---|
| BLDGC24-0593 | Commercial new | 2024-11-19 | Issued | 539 | inspection Above Ceiling/Grid [BLD]: Partial Pass |
| BLDGC24-0479 | Commercial new | 2024-09-20 | Final | 63 | inspection Footing [BLD]: Partial Pass inspection Foundation/Rebar [BLD]: Partial Pass |
| BLDG21-0698 | Commercial alterations | 2021-04-18 | FINALED | 47 | inspection PARTIAL FINAL: PARTIAL PASS inspection DRYWALL-SCREW: PARTIAL PASS inspection ABOVE CEILING/GRID: PARTIAL PASS inspection FIRE STOPPING: PARTIAL PASS inspection DRYWALL-SCREW: NOT READY inspection ROUGH: CONDITIONAL APPROVAL |
| BLDG15-1963 | Commercial alterations | 2015-09-10 | FINALED | 36 | inspection **FINAL: CONDITIONAL APPROVAL inspection ROUGH: PARTIAL PASS inspection PARTIAL ROUGH: PARTIAL PASS inspection DRYWALL-SCREW: PARTIAL PASS |
| BLDGC26-0223 | Commercial alterations | 2026-04-30 | Issued | 21 | plan submittal v1 requires re-submit 4 eReview file(s) sent back for resubmittal |
| BLDG15-2410 | Commercial new | 2015-11-04 | FINALED | 98 | inspection **FINAL: FAILED inspection **FINAL: PARTIAL PASS inspection PARTIAL FINAL: PARTIAL PASS inspection PARTIAL ROUGH: PARTIAL PASS |