Ann Arbor Permit Report Cards

← All ratings

58B+
90% range 55.8–60.2

Trowbridge Companies

Architect · Auburn Hills, MI · #16 of 119 listed overall
Primary kind of workNew homes100% of all permits · #1 of 1 new homes specialists
occasionalhigh confidence

Overall score: 50 = peer average for the same role and the same kind of work (e.g. window jobs are compared with window jobs, remodels with remodels). Based on 33 permits (33 STREAM).

Sub-scores

Inspections56
better than peers
Failed / re-inspection results on 17% of inspections vs 22% expected for similar jobs
Plan quality / Revisions56
better than peers
1.43 plan send-backs / revision events per permit vs 1.94 expected for similar jobs
Time to permit35
worse than peers
Median 85 days to approval vs 63 days peer median (2.17× after adjusting for kind of work)
Completion83
better than peers
0% of issued permits expired/voided without final vs 7% expected
More: compliance & reliability
Compliance61
better than peers
0.26 license/insurance/stop-work type holds per permit vs 0.49 expected
Reliability51
typical
6% of inspections cancelled vs 6% expected

Ann Arbor activity & plain stats

Permits in scored set
33
Last 3 years
3
Last 12 months
0
Years active
1
2023–2023
Median days to approval
85.0
peer median 63.0
Permits needing a revision
54%
Permits with a failed / re-inspection
82%
Inspections on record
265

Job mix

Kinds of work across all 33 permits. Each permit is scored against peers doing the same kind of work.

New homes 100% (33)

Sample permit records

A sample of the public records behind this card. Links open the city's permit portals.

PermitKind of workAppliedStatusDays to approvalNotes
BLDGR23-1133New homes2023-06-05Final56inspection Compaction [BLD]: Re-inspection required
inspection Final [BLD]: Re-inspection required
inspection Rough-In [BLD]: Re-inspection required
plan submittal v2 requires re-submit
plan submittal v1 requires re-submit
2 eReview file(s) sent back for resubmittal
BLDGR23-1139New homes2023-06-05Final63inspection Final [BLD]: Re-inspection required
inspection Rough-In [BLD]: Re-inspection required
plan submittal v1 requires re-submit
plan submittal v2 requires re-submit
2 eReview file(s) sent back for resubmittal
BLDGR23-1134New homes2023-06-05Final462inspection Final [BLD]: Re-inspection required
inspection Final [BLD]: Partial Pass
inspection Rough-In [BLD]: Re-inspection required
plan submittal v2 requires re-submit
plan submittal v1 requires re-submit
2 eReview file(s) sent back for resubmittal
BLDGR23-1176New homes2023-06-09Final707inspection Rough-In [BLD]: Partial Pass
BLDGR23-1182New homes2023-06-09Final26inspection Rough-In [BLD]: Partial Pass
BLDGR23-1180New homes2023-06-09Final593—

Scores update as new permit activity lands. Not a recommendation to hire. Report an error.