49C+
90% range 43.6–55.3
Kasco Construction
Primary kind of workCommercial alterations
activelow confidence
Sub-scores
Inspections51
typical
Failed / re-inspection results on 22% of inspections vs 23% expected for similar jobs
Plan quality / Revisions40
worse than peers
3.84 plan send-backs / revision events per permit vs 1.76 expected for similar jobs
Time to permit42
worse than peers
Median 41 days to approval vs 21 days peer median (2.21× after adjusting for kind of work)
Completion64
better than peers
0% of issued permits expired/voided without final vs 10% expected
More: compliance & reliability
Compliance52
typical
0.13 license/insurance/stop-work type holds per permit vs 0.17 expected
Reliability49
typical
5% of inspections cancelled vs 5% expected
Ann Arbor activity & plain stats
Permits in scored set
6
Last 3 years
3
Last 12 months
1
Years active
4
2019–2025
Median days to approval
41.0
peer median 21.0
Permits needing a revision
83%
Permits with a failed / re-inspection
67%
Inspections on record
73
Job mix
Commercial alterations 67% Commercial new 33%
Sample permit records
| Permit | Kind of work | Applied | Status | Days to approval | Notes |
|---|---|---|---|---|---|
| BLDGC23-0495 | Commercial alterations | 2023-11-14 | Final | 275 | inspection Above Ceiling/Grid [BLD]: Partial Pass inspection Compaction [BLD]: Partial Pass inspection Drywall - Screw [BLD]: Partial Pass |
| BLDGC22-2124 | Commercial new | 2022-06-16 | Final | 343 | plan submittal v4 requires re-submit plan submittal v2 requires re-submit plan submittal v1 requires re-submit plan submittal v3 requires re-submit 3 eReview file(s) sent back for resubmittal Permit placed on hold for more information |
| BLDGC23-0086 | Commercial new | 2023-02-14 | Final | 36 | inspection Final [BLD]: Re-inspection required inspection Footing [BLD]: Partial Pass inspection Foundation/Rebar [BLD]: Partial Pass |
| BLDGC23-0482 | Commercial alterations | 2023-11-07 | Final | 39 | inspection Drywall - Screw [BLD]: Partial Pass inspection Fire Stopping [BLD]: Partial Pass inspection Rough-In [BLD]: Partial Pass plan submittal v1 requires re-submit 1 eReview file(s) sent back for resubmittal |
| BLDGC25-0515 | Commercial alterations | 2025-12-16 | Final | 43 | plan submittal v1 requires re-submit 3 eReview file(s) sent back for resubmittal |
| BLDG19-1046 | Commercial alterations | 2019-06-12 | FINALED | 28 | inspection FOOTING: NOT READY inspection INSULATION: CONDITIONAL APPROVAL inspection ROUGH: CONDITIONAL APPROVAL |
Related Commercial alterations firms
49C+
Metro General Contractors
Commercial alterations
activelow confidence
49C+
TO BE DETERMINED
Commercial alterations
occasionalmedium confidence
50C+
Raves Construction
Commercial alterations
occasionalmedium confidence
49C+
JS Vig Construction Co
Commercial alterations
activefeaturedhigh confidence
49C+
Morningside Broadway, LLC
Commercial alterations
occasionallow confidence